Total Manpower
21
S1: 4 | S2: 17
Works Logged
3
Activities executed
Machinery Deployed
3
Units on site
Cubes Casted
0
QC Samples
1. Work Progress (Site 1 & Site 2)
3 records| Zone | Location / Grid | Activity Description | Unit | Qty Today | Remarks / Delay Cause |
|---|---|---|---|---|---|
| SITE1 | Amphitheatre | RCC | Cum | 10.00 | |
| SITE2 | Food Court | Water proofing | Sqm | 20.00 | |
| SITE2 | Tourist Information Centre | AAC Masonry work | Cum | 5.50 |
2. Manpower Deployment
Total: 21| Site | Trade / Designation | Headcount |
|---|---|---|
| site1 | Barbender | 2 |
| site1 | Carpenter | 2 |
| site2 | Helper (Unskilled) | 6 |
| site2 | Mason | 5 |
| site2 | Mason | 6 |
3. Machinery & Equipment
3 units| Zone | Equipment | Working (Hrs) | Breakdown (Hrs) |
|---|---|---|---|
| site1 | Concrete Mixer | 10.0 | 0.0 |
| site1 | Concrete Mixer | 10.0 | 0.0 |
| site2 | Monkey Lift | 8.0 | 0.0 |
4. Materials Received & Issued
Store In-charge Data| Material | Unit | Received Today | Issued Site 1 | Issued Site 2 | Total Issued | Closing Stock |
|---|---|---|---|---|---|---|
| Cement | Bags | 0.00 | 100.00 | 150.00 | 250.00 | 598.00 |
| Cement | Bags | 0.00 | 100.00 | 150.00 | 250.00 | 598.00 |
5. QA/QC & Testing Records
Quality Control In-charge| Structure / Element | Grade | Pour Card | Slump (mm) | Cubes Cast | Tests Conducted | NCR Status |
|---|---|---|---|---|---|---|
| No QA/QC records entered for this date. | ||||||
Consolidation & WhatsApp Broadcast
Review all submitted entries above before compiling the official PDF and sending the summary to the project WhatsApp group.