RANG GHAR BEAUTIFICATION PROJECT

Centralized Daily Progress Report (DPR) Portal

approved

Total Manpower

15 S1: 4 | S2: 11

Works Logged

2 Activities executed

Machinery Deployed

2 Units on site

Cubes Casted

0 QC Samples

1. Work Progress (Site 1 & Site 2)

2 records
Zone Location / Grid Activity Description Unit Qty Today Remarks / Delay Cause
SITE1 Amphitheatre RCC Cum 10.00
SITE2 Food Court Water proofing Sqm 20.00

2. Manpower Deployment

Total: 15
Site Trade / Designation Headcount
site1 Barbender 2
site1 Carpenter 2
site2 Helper (Unskilled) 6
site2 Mason 5

3. Machinery & Equipment

2 units
Zone Equipment Working (Hrs) Breakdown (Hrs)
site1 Concrete Mixer 10.0 0.0
site2 Monkey Lift 8.0 0.0

4. Materials Received & Issued

Store In-charge Data
Material Unit Received Today Issued Site 1 Issued Site 2 Total Issued Closing Stock
Cement Bags 0.00 100.00 150.00 250.00 598.00

5. QA/QC & Testing Records

Quality Control In-charge
Structure / Element Grade Pour Card Slump (mm) Cubes Cast Tests Conducted NCR Status
No QA/QC records entered for this date.

Consolidation & WhatsApp Broadcast

Review all submitted entries above before compiling the official PDF and sending the summary to the project WhatsApp group.